KEGOC
electrical transfer system reconstruction

Customer Kazakhstan Electricity Grid Operating Company - KEGOC, Kazachstan
Operations subject Gensets
74kVA       9pcs
38kVA       4pcs
19kVA      14pcs
59kVA      59pcs

UPS - uninterruptible power supplies
45kVA         14pcs
40kVA 3/3   14pcs
30kVA 3/3     4pcs
15kVA 3/3     4pcs
Modular UPS    60pcs

Input switchboards     87pcs
Output switchboards  87pcs
Realization 2002 - 2003

Our company has delivered a complex system of back up power supplies for telecommunication equipment, measuring devices and computers. The delivery contains 6 types of sub-deliveries consisting of generating sets, UPS, input and output switchboards and monitoring system.

Kazakhstan regions situated on the south of the country are in a large extent dependent on imported expensive electric energy. For these reasons KEGOC company has decided to build up a north-south line from existing 600MW supply network by using a modern technology. This line will fully replace imported electric energy for all regions. Though KEGOC company conferred management rights to several private companies to co-operate in this field, it itself holds control over all high voltage lines, transformer substations and central dispatching centres.

Delivered complex system of back up power supplies is installed on 85 sites. It backs up and powers telecommunication, transmission and computer equipment on transmission line. Investments used in years 2002 – 2003 were only a part of 258,4 million dollars project for upgrade of transmission line with participation of IBRD bank.